Sunday, April 27, 2014

Trim...

Our lockers are done in the mud room and they look amazing!
Our mantle is done... The two pieces of wood on top has our stain choices.  One is pretty much black and the other is a little lighter.
The island is done as well... 
The trim carpenter has two closets to finish, the pantry and then the trim of the first floor.  Then the painters can start to stain and paint.

Wednesday, April 23, 2014

Cabinets

The cabinets are in...




Jack and Jill bath...
Katie's bath...
Laundry room...
Master bath...

All cabinets are in, but our refrigerator doesn't fit so they will be fixing that!

Monday, April 21, 2014

Trim and more..

Today they started the trim.  Most of the doors upstairs have been hung and they have started with the trim...
The cabinets were delivered ...
Jack and Jill bath...
Kitchen...
Livingroom...
They started the railing...

And started the dog door...

Tomorrow they are supposed to install the cabinets... It is starting to come together!

Friday, April 11, 2014

Drywall

Drywall is 100% complete!  Ceilings are done. Entry way...



Kitchen...
Livingroom...
Mud room...
Master...
Bath...
Closet....
Andrea's room...
I can't wait to see what is finished after we get back next weekend!

Stone

Stone on the outside of the house is finished...



Thursday, April 10, 2014

Sunday, April 6, 2014

drywall is done...

The drywall guys left yesterday at noon.  It took them one day to get the drywall done.  You can now see what the rooms will look like.
The den...

 mudroom...
 arch going into the entry...
 looking from living room into the kitchen...
 kitchen into the living room...
 dinning room...
 going up the stairs...
 Katie's room...
 master...
 looking into master bath and closet...
 master closet...
 Andrea's room...
Alyssa's room...

living room from eat in area...

Now they will come and mud/sand.  The stone will be delivered tomorrow and they will start to install it on Tuesday.